Track the construction progress of Fox Hills, your future home in Lusail City. Every milestone brings us closer to handover.
Overall Progress
38%
Timeline
Q1 2025
CompletedSite secured in Fox Hills district, Lusail City
Q2 2025
CompletedArchitectural plans finalized and government approvals obtained
Q3 2025
CompletedPiling and foundation complete, ground floor slab poured
Q1 2026
CurrentStructural works in progress. Floors 1-3 complete, floors 4-6 underway
38% phase progress
Q3 2026
Mechanical, electrical, plumbing installation and interior finishing
Q1 2027
Facade completion, landscaping, pool, and amenity fit-out
Q3 2027
Final inspections, snagging, and unit handover to owners
Latest Update

March 2026
Floors 1-3 structural framework complete. Floor 4-6 column and slab works are underway. On track for Q3 2026 MEP commencement.
On Schedule
Key Dates
Q1 2025
Construction Start
Q3 2027
Expected Completion
Q4 2027
Handover Begins
30 Months
Total Duration
Our team is available to provide detailed construction updates and answer any questions you may have.